type: project · status: active · area: career · tags: career, mod-ichigaya, jtic, infrastructure

B4RM1 JTIC Buildout

B4RM1 JTIC Buildout

Outcome

New JTIC room (B4RM1) fully operational at MOD Ichigaya by March 2027.

Why It Matters

Stand-up of the new analytical workspace is a primary deliverable of the current MOD Ichigaya site lead role.

Next Actions

Key Decisions Made

Date Decision Rationale
2026-06-29 Fiber spec: 12-core singlemode, LC/LC, ODC-to-ODC Standard for the run
2026-06-29 Working slack: 4m at server-room full rack, 3m at in-room half rack Slack is separate from run length
2026-06-29 Total run length: 800–900 ft (244–274 m) Survey estimate
2026-06-29 Equipment: 36 Analyst + 2 Admin workstations, 30 VoIP phones, 3 printers Room loadout
2026-06-29 Software: 12 SOCET GXP GeoAnalysis + 12 RemoteView Pro licenses Analyst tooling
2026-06-29 Cabling NLT October 2026; DIEE move ~December 2026; project stand-up March 2027 Schedule
2026-06-29 Power upgrade: contractors start 7/1, 2–3 weeks Precedes cabling

Room Move Cascade

DIEE vacates B3RM1 → B5RM8 Training Room moves into B3RM1 → B5RM8 fate TBD.

Key Contacts

Name Role Contact
Matt Lyon Technical authority matt.j.lyon@lmco.com
Brady McCormick Project Manager

Open Questions

Reference Links

Log

2026-06-29

Project note created from Claude history.